Location: Bedfordshire, England
Project Value: 130k
Project Duration: 6 Weeks

Increasing school washroom capacity at Wootton Academy

Cr8tive Washrooms delivered a full turnkey school toilet refurbishment at Wootton Academy in Bedfordshire, converting four underutilised staff washrooms into larger, dedicated student facilities. The project involved structural alterations, compliance works and a complete washroom fit-out. The result is a modern, hygienic and durable set of washroom facilities designed specifically for the demands of a busy secondary school.

The brief

The school's existing washrooms were insufficient for the number of pupils attending the academy, and the layout created unnecessary movement through the building during break times. We needed a practical solution that would:

  • Increase washroom capacity for pupils without significant new-build works

  • Restrict access through the school building during break and lunch periods

  • Create clearly separated male and female facilities with appropriate privacy

  • Deliver a finish that was durable, hygienic and easy for staff to maintain

Cr8tive Washrooms worked with the school to design a solution that addressed all of these needs within the constraints of the existing building footprint.

Design specifications

The school's existing washrooms were insufficient for the number of pupils attending the academy, and the layout created unnecessary movement through the building during break times. We needed a practical solution that would:

  • Increase washroom capacity for pupils without significant new-build works

  • Restrict access through the school building during break and lunch periods

  • Create clearly separated male and female facilities with appropriate privacy

  • Deliver a finish that was durable, hygienic and easy for staff to maintain

Cr8tive Washrooms worked with the school to design a solution that addressed all of these needs within the constraints of the existing building footprint.

Scope of works

The school's existing washrooms were insufficient for the number of pupils attending the academy, and the Cr8tive Washrooms managed the complete turnkey delivery of the project, encompassing all structural, mechanical and fit-out elements under a single contract. The full scope included:

  • Removal of internal dividing walls between four staff washroom facilities to create enlarged male and female pupil suites

  • The formation of new external door openings to allow direct access from outside during break times

  • Full structural and building control compliance works associated with the change of use and structural alterations

  • Fire safety compliance works in accordance with current regulations

  • Supply and installation of full-height compact laminate cubicles, wall cladding, custom Corian-type wash troughs and high-clarity safety vinyl flooring

  • Mechanical and electrical works, including ventilation and lighting

  • Final snagging, deep clean and handover

Key challenges

Structural alterations within a live school building

The conversion of staff facilities into larger pupil washrooms required the removal of internal walls and the creation of new external door openings. Cr8tive Washrooms managed the full compliance process, ensuring the project was delivered in accordance with all current regulations, programmed to minimise disruption to the school day.

Improving access and safeguarding during break times

A key design objective was to reduce pupil movement through the school building during unstructured periods. By creating new external door openings, access during break and lunch times could be managed directly from the playground or external areas.

Specifying for heavy educational use

building type, with hundreds of pupils per day going in and out. Every material selected for this project was chosen with that intensity in mind to deliver long service life with manageable maintenance requirements.

The result

The completed refurbishment project has delivered modern, compliant and functional washroom facilities for the school's pupils. Washroom capacity was significantly increased through the conversion of existing staff facilities, and the new full-height cubicles provide appropriate privacy for secondary-age pupils.

New external access points support better pupil management during break and lunch periods, and all materials were chosen to be durable and hygienic to meet the demands of a busy secondary school. The project demonstrates how thoughtful design and specification, combined with compliant construction management, can transform existing building features into fit-for-purpose educational washroom facilities.

Choose Cr8tive Washrooms for school washroom refurbishment

Previous
Previous

DMG Media Group (The Daily Mail Group)

Next
Next

John Leggott College